<div>A firm protested the Environmental Protection Agency's (EPA) rejection of its bid and subsequent contract award for automotive emissions testing, contending that EPA unreasonably evaluated the bidders' relative past performance and erroneously eliminated its bid from the competitive range. GAO held that: (1) EPA reasonably evaluated the bidders' past performance; and (2) the protester untimely filed its comments on EPA's report on the supplemental protest more than 5 days after receiving the report. Accordingly, the initial protest was denied and the supplemental protest was dismissed.</div>

Matter of: California Environmental Engineering File: B-274807; B-274807.2 Date: January 3, 1997 * Redacted Decision

DIGEST

Attorneys

DECISION

California Environmental Engineering (CEE) protests the exclusion of its proposal from the competitive range and the award of a contract to EG&G- Automotive Research, Inc. under request for proposals (RFP) No. D600007M1, issued by the Environmental Protection Agency (EPA) for automotive emissions testing.

We deny the initial protest and dismiss the supplemental protest.

The RFP provided for the award of a level-of-effort, cost-plus-fixed-fee (CPFF) contract for the operation of the federally-owned Virginia Testing Laboratory in Alexandria, Virginia, for a base with 2 option years. The contractor will be required to procure privately-owned vehicles, which would be tested in accordance with stated federal test procedures and to analyze emissions test failures. Offerors were also informed that in performing the contract they should “provide approximately 108 to 180 vehicles in order to perform approximately 360 tests within each contract period.” Detailed guidelines for obtaining privately-owned vehicles for testing were provided by the RFP. The stated level-of-effort was 16,544 direct labor hours for each contract year; as amended, the RFP identified the estimated level-of-effort for the labor categories to be used in contract performance.

The RFP provided for award on a best value basis and stated that technical quality was more important than cost or price. The following technical evaluation factors and associated point scores were identified:

Past Performance 25

Adequacy of Personnel Qualifications 20

Technical Approach 15

Corporate Experience 10

Proposed Management Plan 10

Mentor Protege Program Plan 10

Quality Assurance Program Plan 5

Quality Assurance Project Plan 5

TOTAL AVAILABLE POINTS 100

The RFP also stated that the agency would evaluate whether offerors were “small business concerns which are also labor surplus area concerns and other small business concerns,” but that these factors, which would not be point scored, were of less importance to both technical quality and cost/price. [1]

Proposals were received from 3 offerors, including CEE and EG&G (the incumbent contractor), and evaluated as follows:

SCORE CPFF

EG&G 92 $2,895,949

Offeror A 44 $2,190,565

CEE 40 $3,197,537

EPA determined that only EG&G’s proposal was acceptable. Specifically, EG&G’s proposal received superior scores under all evaluation factors, reflecting, among other things, EG&G’s excellent past performance and experience as the incumbent contractor, technical approach to performing the contract, and personnel. While CEE’s past performance was assessed as above average, receiving 20 of the 25 available points for this factor, its proposal was considered unacceptable under all but one of the remaining evaluation factors. The contracting officer determined that because CEE’s proposal could not be made acceptable without major proposal revisions, such that CEE did not have a reasonable chance of receiving award, CEE’s proposal was not in the competitive range.

CEE’s initial protest that its proposal was erroneously eliminated from the competitive range is based on its contention that EPA misevaluated the relative past performance of EG&G and CEE. Specifically, CEE argues that EG&G had performance problems under the prior Virginia Testing Laboratory contract, which should have resulted in a lower technical evaluation under the past performance. In contrast, CEE argues that because of its performance of vehicle emissions testing for the State of California, it should have received a higher technical score under this factor.

In determining whether a particular evaluation conclusion is rational, we examine the record to determine whether the judgment was reasonable and in accord with the evaluation criteria listed in the solicitation. Abt Assocs., Inc., B-237060.2, Feb. 26, 1990, 90-1 CPD Para. 223. A protester’s mere disagreement with the agency’s evaluation determination does not demonstrate that the evaluation was unreasonable. Brunswick Defense, B-255764, Mar. 30, 1994, 94-1 CPD Para. 225. Here, the record provides no basis to question EPA’s evaluation of EG&G’s or CEE’s proposals under the past performance factor.

EPA found that EG&G had over 18 years of past performance performing emission testing and restorative maintenance and in managing laboratory contracts; specifically, EG&G had specific experience managing the Virginia Testing Laboratory, as well as the National Vehicle Fuels and Emissions Laboratory. EG&G was found to generally meet performance goals within or below costs on its contract and, in particular, to have satisfactorily performed the current Virginia Testing Laboratory contract within cost. On this basis, EG&G’s past performance received 25 of the available 25 points under the past performance factor.

While CEE complains that EG&G’s past performance of the current contract should not have been evaluated as satisfactory, based upon the protester’s definition of satisfactory performance, the record supports EPA’s evaluation conclusions. For example, while CEE argues that EG&G did not consistently “capture the high-ranked, prioritized vehicles” for testing, EPA explains that this is generally not within the control of the contractor because, among other things, the contractor must select automobiles from a randomized list of vehicles provided by each state’s motor vehicle administration. Thus, CEE has provided no basis to conclude that EG&G’s past performance was overrated. [2]

The record also supports EPA’s evaluation of CEE’s past performance. EPA found that CEE had experience performing exhaust emissions testing and restorative maintenance and managing laboratory contracts, and on this basis CEE’s proposal was assessed as very good under the past performance factor, receiving 20 of the available 25 points. CEE’s past performance was somewhat downgraded because its past performance primarily involved procuring fleet or specialized vehicles rather than vehicles from the general public, as required under this RFP. CEE’s argument that it should have received a higher technical score than EG&G for this factor is nothing more than a mere disagreement with the agency’s technical judgment that does not demonstrate that the evaluation was unreasonable. [3] Moreover, the record establishes that, even if CEE’s proposal received a perfect past performance score, its proposal would still have been found unacceptable and excluded from the competitive range, given CEE’s unacceptable ratings under most of the remaining evaluation factors. [4]

After receipt of the agency report filed in response to the initial protest, which provided the details as to why CEE’s proposal was eliminated from the competitive range, CEE protested a number of other aspects of EPA’s evaluation of CEE’s and EG&G’s proposals. In order to decide these new protest allegations within the time established for our decision on the initial protest, we invoked the accelerated schedule provisions of our Bid Protest Regulations, sections 21.9, 21.10, 61 Fed. Reg. 39039, 39046 (1996) (to be codified at 4 C.F.R. Sec. 21.9, 21.10). As the protester was informed, pursuant to this accelerated schedule, CEE’s comments on the agency’s report on its supplemental protest were required to be filed within 5 calendar days of receipt of the accelerated report. CEE received EPA’s supplemental report on December 6, 1996, which meant that its comments were required to be filed by 5:30 p.m. eastern time on December 11. Section 21.0(g), 61 Fed. Reg. at 39043 (to be codified at 4 C.F.R. Sec. 21.0(g)). CEE untimely filed its comments on the supplemental agency report by facsimile transmission at 6:10 p.m., December 11.

Our Bid Protest Regulations contain strict rules requiring the timely submission of protests, comments, and requests for reconsideration. These filing deadlines are prescribed under the authority of the Competition in Contracting Act of 1984, as amended by the Federal Acquisition Streamlining Act of 1994; their purpose is to enable us to comply with the statutory mandate that we resolve protests expeditiously without unduly delaying or disrupting the procurement process. See 31 U.S.C. Sec. 3554(a) (1994); Green Management Corp.–Recon., B-233598.2, Feb. 27, 1989, 89-1 CPD Para. 208. To avoid delay in the resolution of protests, our Regulations provide that a protester’s failure to file comments within the time required, or to request an extension of time for submitting comments, will result in the dismissal of the protest. Sections 21.3(i), 21.10(d)(2), 61 Fed. Reg. at 39044, 39046 (to be codified at 4 C.F.R. Sec. 21.3(i), 21.10(d)(2)).

We dismiss CEE’s supplemental protest because the protester failed to file its comments within the time required. Although CEE requests that we consider its admittedly untimely filed comments under the good cause exception of section 21.2(c), 61 Fed. Reg. at 39043 (to be codified at 4 C.F.R. Sec. 21.2(c)), as indicated by the express language of our Regulations, this exception is only considered in connection with the late-filing of protests and is not applicable to untimely filed comments. Marconi Elecs., Inc.–Recon., 64 Comp.Gen. 331 (1985), 85-1 CPD Para. 289.

The initial protest is denied and the supplemental protest is dismissed.

Comptroller General of the United States

1. While the protester initially argued that its small business status was not accounted for in the evaluation, the record demonstrates that this factor was considered, but CEE’s numerous other proposal deficiencies caused its proposal to be eliminated from the competitive range.

2. CEE also challenged EPA’s evaluation of EG&G’s proposal under the adequacy of personnel qualifications factor, contending that EG&G was proposing its incumbent personnel who were allegedly misperforming the current Virginia Testing Laboratory contract. Given our denial of CEE’s challenge to EPA’s evaluation of EG&G past performance of this contract, this provides no basis to question EPA’s evaluation of the adequacy of EG&G’s proposed personnel.

3. CEE’s allegation that its slightly lower past performance evaluation factor score was attributable to EPA’s bias against CEE or for EG&G is unsupported by the record. Where a protester alleges bias on the part of government officials, the protester must provide credible evidence clearly demonstrating a bias against the protester or for the awardee, and that the agency’s bias translated into action that unfairly affected the protester’s competitive position. Advanced Sciences, Inc., B-259569.3, July 3, 1995, 95-2 CPD Para. 52. The fact that some evaluators were responsible for overseeing EG&G’s performance of the Virginia Testing Laboratory contract provides no basis for questioning these evaluators’ conclusions.

4. CEE also complains that its proposed cost should have been evaluated as lower than EG&G’s if the agency had considered CEE’s cost per vehicle. This contention is based on CEE’s assertion that it promised to provide at least 180 vehicles each year under the designated level-of-effort, while EG&G allegedly would only provide 108 vehicles under this level-of-effort. This argument is meritless. The RFP did not provide that offerors’ estimated costs would be compared by determining a cost per vehicle provided for testing. Rather, offerors were apprised that their proposed costs would be evaluated in reference to the RFP’s estimated level-of- effort for each labor category, which is precisely the method by which EPA evaluated EG&G’s and CEE’s proposed costs. Moreover, EG&G’s proposal did not limit its performance to providing only 108 vehicles per year for testing, as CEE’s supposes, but promised to satisfy the RFP requirements, which provide for between 108 and 180 vehicles. Thus, there is no basis for the cost per vehicle comparison argued by CEE. See The Research Foundation of State University of New York , B-274269, Dec. 2, 1996, 96-2 CPD Para. 207. In any case, CEE’s proposal was eliminated from the competitive range because it was rated unacceptable under the majority of the technical factors, not because of its higher-evaluated cost.

DOCUMENT FOR PUBLIC RELEASE A protected decision was issued on the date below and was subject to a GAO Protective Order. This version has been redacted or approved by the parties involved for public release.

More from:

News Network

  • Secretary Antony J. Blinken with Lotfullah Najafizada of TOLO News
    In Crime Control and Security News
    Antony J. Blinken, [Read More…]
  • Judiciary Informs Congress of Its Opposition to Bill
    In U.S Courts
    The Judiciary has informed Congress that it opposes the proposed Judiciary Accountability Act. In a letter to key lawmakers today, Judge Roslynn R. Mauskopf, secretary of the Judicial Conference of the United States, wrote that the bill “fails to recognize the robust safeguards that have been in place within the Judiciary to protect Judiciary employees, including law clerks, from wrongful conduct in the workplace, including protections against discrimination, harassment, retaliation, and abusive conduct.”
    [Read More…]
  • Sanctioning Cuban Officials in Response to Violence against Peaceful Protestors
    In Crime Control and Security News
    Antony J. Blinken, [Read More…]
  • Marking the Fourth Anniversary of the Ethnic Cleansing in Rakhine State
    In Crime Control and Security News
    Ned Price, Department [Read More…]
  • John Kerry Virtual Leaders Summit on Climate Day One Closing Remarks
    In Climate - Environment - Conservation
    John Kerry, Special [Read More…]
  • F-35 Sustainment: Enhanced Attention to and Oversight of F-35 Affordability Are Needed
    In U.S GAO News
    What GAO Found F-35 mission capable rates—a measure of the readiness of an aircraft fleet—have recently improved, but still fall short of warfighter requirements, as discussed in our draft report. Specifically, from fiscal year 2019 to fiscal year 2020, the U.S. F-35 fleet's average annual (1) mission capable rate—the percentage of time during which the aircraft can fly and perform one of its tasked missions—improved from 59 to 69 percent; and (2) full mission capable rate—the percentage of time during which the aircraft can perform all of its tasked missions—improved from 32 to 39 percent. Both metrics fall below the services' objectives. For example, in fiscal year 2020 the Air Force F-35A full mission capable rate was 54 percent, versus a 72 percent objective. Since 2012, F-35 estimated sustainment costs over its 66-year life cycle have increased steadily, from $1.11 trillion to $1.27 trillion, despite efforts to reduce costs. The services face a substantial and growing gap between estimated sustainment costs and affordability constraints—i.e., costs per tail (aircraft) per year that the services project they can afford—totaling about $6 billion in 2036 alone (see fig.). The services will collectively be confronted with tens of billions of dollars in sustainment costs that they project as unaffordable during the program. Gap between F-35 Affordability Constraints and Estimated Sustainment Costs in 2036 Note: Costs are in constant year 2012 dollars as that was the year when the F-35 program was most recently re-baselined. aSteady state years for the F-35 program are defined in each respective service's affordability analysis as: US Air Force/F-35A – 2036-2041; US Marine Corps/F-35B – 2033-2037; US Navy/F-35C – 2036-2043. Steady state refers to the program's peak operating point. The Air Force needs to reduce estimated costs per tail per year by $3.7 million (or 47 percent) by 2036 or it will incur $4.4 billion in costs beyond what it currently projects it could afford in that year alone. Cost reductions become increasingly difficult as the program grows and matures. However, GAO found there is no agreed upon approach to achieve the constraints. Without an assessment of cost-reduction efforts and program requirements (such as number of planned aircraft), along with a plan, the Department of Defense (DOD) may continue to invest resources in a program it ultimately cannot afford. Congress requiring DOD to report on its progress in achieving affordability constraints and making F-35 procurements contingent on DOD's demonstrated progress would enhance DOD's accountability for taking the necessary and appropriate actions to afford sustaining the F-35 fleet. Why GAO Did This Study The F-35 aircraft with its advanced capabilities represents a growing portion of DOD's tactical aviation fleet—with the Air Force, Marine Corps, and Navy currently flying about 400 of the aircraft. It is also DOD's most ambitious and costly weapon system in history, with estimated life-of-program costs exceeding $1.7 trillion. DOD plans to procure nearly 2,500 F-35s at an estimated total acquisition cost of just under $400 billion. The remaining $1.3 trillion in life cycle costs is associated with operating and sustaining the aircraft. This statement, among other things, assesses the extent to which (1) the F-35 has met warfighter-required mission capable rates; and (2) DOD has reduced the F-35's estimated life cycle sustainment costs and made progress in meeting its affordability constraints. This statement is largely based on GAO's draft report, which was provided to DOD in March for review and comment. For that report and this statement, GAO reviewed program documentation, analyzed performance and cost data, collected data from F-35 locations, and interviewed officials.
    [Read More…]
  • Former Mississippi Police Officer Pleads Guilty to Excessive Force Charge
    In Crime News
    The Justice Department announced today that a former officer with the Meridian, Mississippi Police Department pleaded guilty to using excessive force against a man during a vehicle stop and arrest. 
    [Read More…]
  • Rebuilding Iraq: Status of Funding and Reconstruction Efforts
    In U.S GAO News
    Rebuilding Iraq is a U.S. national security and foreign policy priority and constitutes the largest U.S. assistance program since World War II. Billions of dollars in grants, loans, assets, and revenues from various sources have been made available or pledged to the reconstruction of Iraq. The United States, along with its coalition partners and various international organizations and donors, has embarked on a significant effort to rebuild Iraq following multiple wars and decades of neglect by the former regime. The U.S. effort to restore Iraq's basic infrastructure and essential services is important to attaining U.S. military and political objectives in Iraq and helping Iraq achieve democracy and freedom. This report provides information on (1) the funding applied to the reconstruction effort and (2) U.S. activities and progress made in the oil, power, water, and health sectors and key challenges that these sectors face.As of March 2005, the United States, Iraq, and international donors had pledged or made available more than $60 billion for security, governance, and reconstruction efforts in Iraq. The United States provided about $24 billion (for fiscal years 2003 through 2005) largely for security and reconstruction activities. Of this amount, about $18 billion had been obligated and about $9 billion disbursed. The State department has reported that since July 2004, about $4.7 billion of $18.4 billion in fiscal year 2004 funding has been realigned from large electricity and water projects to security, economic development, and smaller immediate impact projects. From May 2003 through June 2004, the Coalition Provisional Authority (CPA) controlled $23 billion in Iraqi revenues and assets, which was used primarily to fund the operations of the Iraqi government. The CPA allocated a smaller portion of these funds--about $7 billion--for relief and reconstruction projects. Finally, international donors pledged $13.6 billion over 4 years (2004 through 2007) for reconstruction activities, about $10 billion in the form of loans and $3.6 billion in the form of grants. Iraq had accessed $436 million of the available loans as of March 2005. As of the same date, donors had deposited more than $1 billion into funds for multilateral grant assistance, which disbursed about $167 million for the Iraqi elections and other activities, such as education and health projects. The U.S. reconstruction effort in Iraq has undertaken many activities in the oil, power, water, and health sectors and has made some progress, although multiple challenges confront each sector. The U.S. has completed projects in Iraq that have helped to restore basic services, such as rehabilitating oil wells and refineries, increasing electrical generation capacity, restoring water treatment plants, and reestablishing Iraqi basic health care services. However, as of May 2005, Iraq's crude oil production and overall power generation were lower than before the 2003 conflict, although power levels have increased recently; some completed water projects were not functioning as intended; and construction at hospital and clinics is under way. Reconstruction efforts continue to face challenges such as rebuilding in an insecure environment, ensuring the sustainability of completed projects, and measuring program results.
    [Read More…]
  • Human smuggling recruiter sentenced for conspiracy
    In Justice News
    A 58-year-old Chandler [Read More…]
  • Stabilization and Reconstruction: Actions Are Needed to Develop a Planning and Coordination Framework and Establish the Civilian Reserve Corps
    In U.S GAO News
    In 2004, the Department of State created the Office of the Coordinator for Reconstruction and Stabilization to coordinate U.S. planning and implementation of stabilization and reconstruction operations. In December 2005, President Bush issued National Security Presidential Directive 44 (NSPD-44), charging State with improving coordination, planning, and implementation of such operations and ensuring that the United States can respond quickly and effectively to overseas crises. GAO was asked to report on State's efforts to improve (1) interagency planning and coordination for stabilization and reconstruction operations, and (2) deployment of civilians to these operations. To address these objectives, we conducted interviews with officials and reviewed documents from U.S. agencies and government and private research centers.The office of the Coordinator for Reconstruction and Stabilization (S/CRS) is developing a framework for planning and coordinating U.S. reconstruction and stabilization operations. The National Security Council (NSC) has adopted two of three primary elements of the framework--the Interagency Management System and procedures for initiating the framework's use. However, the third element--a guide for planning stabilization and reconstruction operations--is still in progress. We cannot determine how effective the framework will be because it has not been fully applied to any stabilization and reconstruction operation. In addition, guidance on agencies' roles and responsibilities is unclear and inconsistent, and the lack of an agreed-upon definition for stabilization and reconstruction operations poses an obstacle to interagency collaboration. Moreover, some interagency partners stated that senior officials have shown limited support for the framework and S/CRS. Some partners described the new planning process, as presented in early versions of the planning guide, as cumbersome and too time consuming for the results it has produced. S/CRS has taken steps to strengthen the framework by addressing some interagency concerns and providing training to interagency partners. However, differences in the planning capacities and procedures of civilian agencies and the military pose obstacles to effective coordination. State has begun developing three civilian corps that can deploy rapidly to international crises, but key details for establishing and maintaining these units remain unresolved. First, State created the Active Response Corps (ARC) and the Standby Response Corps (SRC) comprised of U.S. government employees to act as first responders to international crises and has worked with several agencies to create similar units. However, these efforts are limited due to State's difficulty in achieving planned staffing levels for ARC, a lack of training available to SRC volunteers, other agencies' inability to secure resources for operations unrelated to their core domestic missions, and the possibility that deploying employees to such operations can leave units without sufficient staff. Second, in 2004, State began developing the Civilian Reserve Corps (CRC). CRC would be comprised of U.S. civilians who have skills and experiences useful for stabilization and reconstruction operations, such as police officers, civil engineers, public administrators, and judges that are not readily available within the U.S. government. If deployed, volunteers would become federal workers. S/CRS developed a plan to recruit the first 500 volunteers, and NSC has approved a plan to increase the roster to 2,000 volunteers in 2009. In May 2007, State received the authority to reallocate up to $50 million to support and maintain CRC, but it does not yet have the authority to obligate these funds. In addition, issues related to volunteers' compensation and benefits that could affect CRC recruitment and management would require congressional action. Furthermore, State has not clearly defined the types of missions for which CRC would be deployed. State has estimated the costs to establish and sustain CRC at home, but these costs do not include costs for deploying and sustaining volunteers overseas.
    [Read More…]
  • Cameroonian Citizen Extradited from Romania to Face Covid-19-Related Fraud Charges
    In Crime News
    A citizen of Cameroon was extradited to the U.S. yesterday to face federal charges for his alleged involvement in a fraud scheme perpetrated against American consumers.
    [Read More…]
  • Secretary Antony J. Blinken With Yalda Hakim of “Impact with Yalda Hakim” on BBC World News
    In Crime Control and Security News
    Antony J. Blinken, [Read More…]
  • Veterans’ Disability Benefits: Processing of Claims Continues to Present Challenges
    In U.S GAO News
    The Subcommittee on Disability Assistance and Memorial Affairs, House Veterans' Affairs Committee, asked GAO to discuss its recent work related to the Department of Veterans Affairs' (VA) disability claims and appeals processing. GAO has reported and testified on this subject on numerous occasions. GAO's work has addressed VA's efforts to improve the timeliness of decisions on claims and appeals and VA's efforts to reduce backlogs.VA continues to face challenges in improving service delivery to veterans, specifically speeding up the process of adjudication and appeal, and reducing the existing backlog of claims. For example, as of the end of fiscal year 2006, rating-related compensation claims were pending an average of 127 days, 16 days more than at the end of fiscal year 2003. During the same period, the inventory of rating-related claims grew by almost half, in part because of increased filing of claims, including those filed by veterans of the Iraq and Afghanistan conflicts. Meanwhile, appeals resolution remains a lengthy process, taking an average of 657 days in fiscal year 2006. However, several factors may limit VA's ability to make and sustain significant improvements in its claims-processing performance, including the potential impacts of laws and court decisions, continued increases in the number and complexity of claims being filed, and difficulties in obtaining the evidence needed to decide claims in a timely manner, such as military service records. VA is taking steps to address these problems. For example, the President's fiscal year 2008 budget requests an increase of over 450 full-time equivalent employees to process compensation claims. VA is also working to improve appeals timeliness by reducing appeals remanded for further work. While VA is taking actions to address its claims-processing challenges, opportunities for significant performance improvement may lie in more fundamental reform of VA's disability compensation program. This could include reexamining program design such as updating the disability criteria to reflect the current state of science, medicine, technology, and labor market conditions. It could also include examining the structure and division of labor among field offices.
    [Read More…]
  • [Protest of Army Contract Award for Commissary Construction]
    In U.S GAO News
    A firm protested an Army contract award for commissary design and construction, contending that the Army failed to: (1) follow the specified criteria in evaluating the awardee's proposal; and (2) maintain the integrity of the competitive bidding system, since it did not award the contract to the low, technically acceptable bidder. GAO held that the Army: (1) reasonably evaluated proposals and assigned additional points for innovative or creative design features that exceeded commercial standards; and (2) properly awarded to the higher-priced, technically superior bidder. Accordingly, the protest and claim for reimbursement for bid and protest preparation costs were denied.
    [Read More…]
  • Briefing with Consular Affairs Acting Deputy Assistant Secretary for Visa Services Julie M. Stufft on the Current Status of Immigrant Visa Processing at Embassies and Consulates
    In Crime Control and Security News
    Julie M. Stufft, [Read More…]
  • Election of Fiame Naomi Mata’afa as Prime Minister of Samoa
    In Crime Control and Security News
    Ned Price, Department [Read More…]
  • K-12 Education: School Districts Need Better Information to Help Improve Access for People with Disabilities
    In U.S GAO News
    Two-thirds of U.S. public school districts have schools with physical barriers that may limit access for people with disabilities, according to GAO's survey of district officials. Barriers, such as a lack of accessible door hardware and steep ramps, can make it challenging for students, teachers, and others with disabilities to use public school facilities (see fig.). In 55 schools across six states, the most common areas with barriers GAO observed were restrooms, interior doorways, and classrooms. GAO also observed barriers related to safety and security. For example, for security, some schools had installed double-door vestibules with limited maneuvering space that could trap people who use wheelchairs. Examples of Doorway and Auditorium Barriers GAO Observed in Schools Note: Barriers presented in this figure potentially limit physical access for people with disabilities, but taken alone, would not necessarily establish whether a legal violation has occurred. An estimated 70 percent of districts had large-scale renovations, small-scale upgrades, or accessibility evaluations planned in the next 3 calendar years, but frequently cited funding constraints as a challenge to these efforts. Districts also identified the need to prioritize projects that keep buildings operational, such as roofing and heating projects. In addition, GAO's survey, observations during site visits, and interviews with national disability groups revealed a tension between making safety and security upgrades and improving physical accessibility. The Department of Justice (Justice) has not provided technical assistance on physical accessibility in schools, and GAO's surveys indicate such help is needed. Justice has authority to provide information on interpreting the Americans with Disabilities Act of 1990 (ADA), including for public schools, and it has provided technical assistance regarding other public facilities, such as stadiums. In addition, Justice, along with the Department of Education (Education) and other federal agencies, recently launched a new website on school safety, but it does not include specific information on how to improve accessibility of public school facilities or provide information on ADA requirements in the context of school safety upgrades. Without such information, federal agencies may miss opportunities to help ensure that people with disabilities have safe and secure access to public school facilities. National reports have raised concerns about the physical accessibility of public school facilities for people with disabilities. These facilities serve important roles as schools, voting locations, and emergency shelters, among other things. GAO was asked to examine the physical accessibility of public school facilities. This report examines the extent to which (1) school districts have school facilities with physical barriers that may limit access for people with disabilities, (2) districts plan to improve the accessibility of school facilities and the challenges they face, and (3) Justice and Education assist districts and states in improving school facilities' physical accessibility. GAO conducted a nationally representative survey of school districts; surveyed states and the District of Columbia; examined 55 schools across six states, selected for variation in size and other characteristics; reviewed relevant federal laws, regulations, and guidance; and interviewed federal, state, and school district officials, and national disability groups. GAO recommends that Justice work with Education to (1) provide information specific to accessibility of public school facilities and (2) provide information on federal accessibility requirements in the context of public school safety and security. Justice neither agreed nor disagreed with GAO's recommendations. For more information, contact Jacqueline M. Nowicki at (617) 788-0580 or nowickij@gao.gov.
    [Read More…]
  • Opening Statement Before the House Committee on Appropriations, Subcommittee on State, Foreign Operations, and Related Programs
    In Crime Control and Security News
    Antony J. Blinken, [Read More…]
  • Department Press Briefing – February 10, 2021
    In Crime Control and Security News
    Ned Price, Department [Read More…]
  • Special Envoy Pham Participates in Ministerial Roundtable for the Central Sahel
    In Crime Control and Security News
    Office of the [Read More…]
Network News © 2005 Area.Control.Network™ All rights reserved.